Precast pier blocks, often sold as deck blocks, are concrete blocks with a slot or bracket on top. They sit on the ground instead of in it. They save hours of digging, but the code limits where you can use them. If your deck falls outside those limits, plan for poured footings and price them with the Sonotube concrete calculator.
What the IRC allows
Section R507.3 of the 2021 IRC lets you skip footings for a freestanding deck only when all of these are true:
- The joists bear directly on precast concrete pier blocks at grade, without support by beams or posts.
- The deck area is no more than 200 square feet.
- The walking surface is no more than 20 inches above grade at any point within 36 inches of the edge.
Some towns change these limits, for example by setting a different height. Ask for your local deck handout.
When pier blocks are a good fit
- A low platform deck in the yard, not touching the house
- A path of decking over level ground
- A base for a small, light shed where your code allows it
When you need a real footing
- The deck is attached to the house. The ledger ties the deck to a foundation that does not move, so the deck footings must not move either.
- The deck is high enough to need posts and beams.
- The deck is bigger than 200 sq ft.
- Frost heave is common where you live and you want the deck to stay level.
In those cases the usual answer is poured concrete in form tubes below the frost line. See deck footing options for the alternatives and deck footing requirements for what the inspector checks.
How to set pier blocks level
- Strip the sod and loose topsoil where each block goes.
- Add a few inches of compacted gravel so water drains away from the block.
- Set the block and check it for level in both directions.
- Run a string or use a long level across the blocks so the tops line up. Adjust with gravel, not shims.
- Set the joists in the slots and fasten them as the block maker shows.
Cost compared with poured footings
Example: a 10 × 12 ft platform deck
A low freestanding platform, 120 sq ft, built 10 inches off the ground:
- Framing: joists running the 10 ft direction, 24 inches apart, so 7 joists across the 12 ft width.
- Blocks: one block under each joist at both ends and at the middle of its span, so the joists bear directly on the blocks: 7 × 3 = 21 blocks.
- Code check: 120 sq ft is under 200, the joists bear directly on precast blocks at grade, and the walking surface is well under 20 inches. Under the 2021 IRC exception, no footings are required.
Check joist size and block spacing against a span table or your plan. If the same deck were raised on posts and beams to 3 ft, or bolted to the house, it would need footings.
The gravel base
The base under each block does more work than the block itself:
- Dig out sod and soft topsoil, usually a few inches.
- Fill with crushed gravel in thin layers and tamp each layer firm.
- Make the gravel pad a little wider than the block so the edges do not sink.
- Slope the ground under the deck so water drains away rather than pooling around the blocks.
Common mistakes
- Setting blocks straight on grass or loose soil, which settles unevenly.
- Using the post slot to raise the deck high, which takes the deck out of the code exception.
- Attaching the platform to the house. Once attached, it is no longer freestanding.
- Spacing blocks farther apart than the joists can span.
When to step up to footings
If any of these change, plan for poured footings instead: the deck grows past 200 sq ft, it rises more than 20 inches near an edge, it gets posts and beams, or it ties into the house. A poured footing for a light deck is often a 10 inch tube 3 ft deep: about 1.64 cu ft and 3 bags of 80 lb mix each.
Frost heave and blocks
Blocks on the surface sit in the layer of soil that freezes. In areas with frost, they can rise in winter and settle unevenly in spring. On a freestanding platform this shows up as a deck that rocks or has a low corner, which you can fix by re-leveling the blocks. On an attached deck the same movement would push against the house, which is why the code does not allow it.
Good drainage helps: gravel under each block, ground sloped away, and no downspout emptying under the deck.
Check them once a year
Walk around the deck each spring. Look for blocks that have tilted, sunk or lifted, joists that no longer sit fully in their slots, and soil washed out from under the gravel. Re-level and reset anything that moved. It takes minutes on a low deck and keeps the frame from twisting.
Quick answers
- Allowed for: small, low, freestanding decks that meet the code exception.
- Not allowed for: decks attached to the house, decks with posts and beams, decks over 200 sq ft or more than 20 inches up near the edge, under the 2021 IRC.
- Base: compacted gravel on firm soil, not grass.
- Upkeep: check and re-level once a year in frost areas.
Pier blocks cost little each and need no digging. Six poured footings in 10 inch tubes at 3 ft take about 18 bags of 80 lb mix with 10% waste, plus tubes and post bases, and a day of work. Open that comparison and add your bag price to see the concrete cost.