A pole barn puts the whole building on its posts, so each footing carries a share of the roof, snow and wind loads. That makes pole barn footing size an engineering number, usually printed on the plans the building kit or designer provides. This guide explains the common setups and how to count the concrete with the Sonotube concrete calculator.
Three common footing setups
| Setup | How it works | Notes |
|---|---|---|
| Pad under an embedded post | A precast or poured concrete pad at the bottom of the hole; the treated post stands on it and the hole is backfilled or collared | Traditional post-frame method |
| Pad plus concrete collar | Same pad, with concrete poured around the bottom of the post to resist uplift | Often specified for wind uplift |
| Poured pier with bracket | A form tube filled with concrete from the bottom of the hole to above grade, with a wet-set bracket on top | Keeps the wood out of the ground |
Your plans say which one, and give the pad diameter, thickness and depth.
What sets the size
- Post load: roof span, post spacing and the snow load where you build. Heavier snow means bigger pads.
- Uplift: wind trying to lift the roof. Collars, uplift anchors or deeper piers resist it.
- Soil: weaker soil needs a bigger pad for the same load.
- Frost depth: the bottom of the footing goes below it. See frost line depth.
Concrete for a 30 × 40 ft barn
Example layout: posts 8 ft apart on the 40 ft walls (6 per side) and one middle post on each 30 ft end wall, so 14 posts. Each on an 18 inch poured pier 4 ft deep.
| Item | Amount |
|---|---|
| One pier | 7.07 cu ft |
| 14 piers | 98.96 cu ft (3.67 cu yd) |
| With 10% waste | 108.86 cu ft (4.03 cu yd) |
| 80 lb bags | 182 |
| Ready-mix, rounded | 4.25 cu yd |
At that size, a truck almost always beats bags. Open this layout in the calculator, enter your prices in step 3, and it compares bags with ready-mix including a short-load fee. Change the diameter, depth and count to match your plans.
Pad only
If your plans call for a round pad under each post instead of a full pier, enter the pad as a short tube. A 24 inch pad 8 inches thick is a 24 inch tube 0.67 ft tall: 2.09 cu ft each, or 4 bags of 80 lb. Fourteen of them with 10% waste take 32.2 cu ft, about 54 bags.
Embedded posts vs brackets on piers
| Compare | Embedded post on a pad | Post on a bracket over a pier |
|---|---|---|
| Wood in the ground | Yes, must be rated for ground contact | No, the post starts above grade |
| Concrete per post | A pad, plus a collar if specified | A full pier from the bottom of the hole to above grade |
| Uplift | Collars, uplift cleats or anchors | Bracket and pier weight |
| Concrete cost | Lower | Higher |
| Replacing a post | Hard | Easier |
The engineered plans for the building decide which one you use. Some kits are designed only for one method.
Planning the concrete
- Get the footing schedule from the plans: diameter, thickness or depth, and any collar.
- Count the posts, including door jambs and interior posts if there are any.
- Enter each footing type as its own row in the calculator: piers as tubes, pads as short tubes, square pads as a pad footing.
- Add 10% for waste. Holes for big posts are rarely neat.
- Compare bags and ready-mix in step 3. At pole barn volumes, ready-mix usually wins.
Ordering ready-mix for a barn
- Tell the supplier the total in cubic yards, rounded up, and that it is for post footings.
- Ask whether the truck can reach every hole. If not, plan a wheelbarrow crew, a buggy, or pour in sections.
- Have every hole dug, inspected if required, and ready before the truck arrives. Waiting time is often charged.
- Have a plan for leftover concrete, such as forms for a small pad or step.
Inspection
Many jurisdictions inspect post holes before concrete, the same as deck footings. Keep the plans on site and call for the inspection when the holes are dug to depth and any pads or forms are set.
Concrete in large tubes
Pole barn piers often use bigger tubes than decks. Per pier, no waste:
| Tube | Per foot | 4 ft pier | 80 lb bags (4 ft) |
|---|---|---|---|
| 18 in | 1.77 cu ft | 7.07 cu ft | 12 |
| 24 in | 3.14 cu ft | 12.57 cu ft | 21 |
| 30 in | 4.91 cu ft | 19.63 cu ft | 33 |
Large tubes hold a lot of concrete and push hard on their sides when full. Backfill and brace them well, and pour in lifts.
Common mistakes
- Sizing pads from a neighbor’s barn instead of your plans. Snow load, span and soil differ from site to site.
- Forgetting door jamb posts and interior posts when counting footings.
- Ordering ready-mix before every hole is dug and inspected.
- Backfilling with the clay that came out of the hole in wet areas, which holds water around the posts. Follow the plans for backfill material.
Quick answers
- Footing size: from the engineered plans, set by post load, snow and wind loads, and soil.
- Common pier tubes: 18 to 24 inches, larger for heavy buildings.
- Depth: below the frost line and as deep as the plans require for uplift and side loads.
- Concrete for 14 piers, 18 in × 4 ft: about 4 cubic yards with 10% waste, usually a ready-mix job.
For smaller buildings on piers, see concrete pier foundation.