How to Pour Concrete Deck Footings with a Sonotube (Step by Step)

By Updated 4 min read

Line drawing illustrating concrete deck footing

Quick answer

Lay out the footings with string, dig below the frost line, set and brace each Sonotube, pour concrete in lifts while rodding out air, then set a post base in the center and let it cure. For six 12 inch footings 4 ft deep you need about 35 bags of 80 lb mix with 10% waste. Plan one helper and a mixer.

6 footings, 12 in × 4 ft
35 × 80 lb bags
Water per 80 lb bag
≈3 quarts
Min. depth (IRC)
12 in below grade

Pouring deck footings with form tubes is a one-day job for two people once the holes are dug. The order matters more than the tools. Start by counting bags in the Sonotube concrete calculator so nothing runs out mid-pour.

What you need

  • Form tubes, cut to length (see how to cut a Sonotube), plus bells if your plan uses them
  • Concrete mix: bags from the calculator, plus a spare or two
  • Post bases or anchor bolts, one per footing
  • Post-hole digger or auger, shovel, tape, string, stakes, level
  • Wheelbarrow or mixer, hoe, buckets, a length of rebar or a stick for rodding
  • 2x4 scraps and screws for bracing

The 10 steps

  1. Get the permit and the frost depth. The building department tells you the required depth and whether they inspect before the pour. Frost line depth explains why it matters.
  2. Lay out the footings. Set batter boards, run string lines for the beam, and mark each footing center. Check the diagonals so the layout is square.
  3. Dig. Go a few inches wider than the tube (or the bell) and down to firm, undisturbed soil at the required depth. Clean loose dirt off the bottom.
  4. Set the base. Place the bell or pour the pad if your plan has one.
  5. Set the tubes. Drop each tube in, check it for plumb on two sides, and set the top a few inches above grade. Cut it so all the tops are where you want them.
  6. Brace and backfill. Screw scrap 2x4s across the top and stake them, then backfill around the tube in layers and tamp. A tube that is not backfilled can float or bulge when it fills.
  7. Inspection. If your jurisdiction inspects holes, call now with tubes and rebar in place.
  8. Mix and pour. Mix each bag with about 3 quarts of water, the starting amount Quikrete lists for an 80 lb bag of its concrete mix. Pour in lifts of a foot or two, rodding each lift and tapping the outside of the tube to bring air out.
  9. Set the anchor. Strike the top flat, then push the post base or anchor bolt into the center, using the string line to keep it aligned with the beam. Check it is square to the beam and at the right height.
  10. Cure and strip. Keep the tops damp or covered for a few days in hot weather. Once the concrete has hardened, peel the cardboard off the part above grade with a utility knife.

Concrete for common decks

Per job, 10% waste, 80 lb bags:

Deck footings Concrete 80 lb bags
4 × 10 in tubes, 3 ft 7.20 cu ft 12
6 × 12 in tubes, 4 ft 20.73 cu ft 35
6 × 12 in tubes, 4 ft, bells to 24 in 32.83 cu ft 55
9 × 12 in tubes, 4 ft 31.10 cu ft 52

Bells add a lot, so include them. Beyond about 45 bags, price a small ready-mix load as well.

Water and strength

More water makes concrete easier to pour and weaker once it sets. Quikrete’s data sheet for its concrete mix gives a starting point of about 6 pints (3 quarts) per 80 lb bag and a working range up to about 9 pints. Quikrete also warns that an extra quart per 80 lb bag can cut strength by up to 40%. Add water slowly and stop when the mix holds its shape.

Checklist before you leave the site

  • Every anchor centered, in line and at the right height
  • Tops sloped slightly so water runs off
  • Tubes still plumb after the pour
  • Bags and tools rinsed before concrete sets on them

Mixing: by hand or with a mixer

Compare Wheelbarrow and hoe Electric drum mixer
Good for Up to about 10 to 15 bags 15 bags and up
Batch size One bag at a time Usually one or two bags
Effort Hard on the back Mostly loading and pouring
Cost Tools you likely own Rental or purchase

Whichever you use, add water in steps. Start with about two thirds of the water, add the mix, then add the rest slowly until the concrete is like thick oatmeal and holds its shape.

Weather

  • Hot and windy: concrete dries out at the top. Mist or cover the tops for the first few days.
  • Cold: concrete sets slowly and can be damaged if it freezes while fresh. Avoid pouring when hard frost is expected, or follow cold-weather instructions on the bag.
  • Rain: cover the tubes and the fresh tops. Heavy rain on wet concrete washes out the surface.

Troubleshooting

  • The tube bulged or floated: it was not backfilled enough. Stop, backfill and tamp around it, and continue.
  • The anchor sank or tilted: the concrete was too wet or the anchor was set too early. Reset it and hold it until the mix stiffens.
  • You ran out of concrete mid-footing: finish the footing as soon as possible. A long gap between lifts leaves a weak joint.
  • The top is not level: fine for a post base that sits on top, as long as the base bears fully.

Cleanup

Rinse the mixer, wheelbarrow and tools as soon as the last footing is poured. Concrete that dries on steel is hard to chip off. Do not wash leftover concrete into a storm drain or onto the lawn; let small amounts harden on a tarp or in a cardboard box and dispose of them with construction waste. Empty bags go in the trash, folded flat.

Next: how to attach a deck post to a concrete footing.

Frequently asked questions

Should I fill the Sonotube all at once?

Pour in a few lifts and rod or tap the tube between them so trapped air comes out, but finish the footing in one session so there is no cold joint.

How long before I can build on a concrete footing?

Follow the bag. Standard concrete mix keeps gaining strength for weeks, and most builders wait at least a couple of days before setting posts and loading them, longer in cold weather.

Do I put gravel under a Sonotube?

Many plans call for the footing to bear on undisturbed soil, and some allow or require a compacted gravel base. Follow your plan and ask the inspector before adding gravel.

When do I call for the footing inspection?

Most jurisdictions inspect the holes before you pour, with tubes set and any rebar in place. Check your permit card.

Figures are typical US values for planning. Building codes, product specs and local prices vary, so confirm with your local building department, the product label and your plans or engineer. See how we write and check our guides.